Infrastructure Upgrade Completed Early
Twp Rd 574A Reopens West of Mayerthorpe
The County is pleased to announce that major infrastructure work on Township Road 574A west of Mayerthorpe is officially complete, with the road reopening to full traffic eight days ahead of schedule.
Following intensive summer construction, contractors and Lac Ste. Anne County Public Works crews completed the culvert installation, roadway resurfacing, and transition joint finishing ahead of the original October 15 target completion date.

The newly restored roadway now provides a safe, reliable driving surface for local motorists and school area traffic.
Emergency Response and Scope of Work
The replacement of the culvert over a tributary of Little Paddle River west of Mayerthorpe was escalated to an emergency capital priority following severe structural degradation. Underlying erosion triggered a sinkhole in the roadway near the Mayerthorpe School area, forcing the County to implement a single-lane safety closure.
The situation was further compounded by heavy overland flooding, which overwhelmed the aging structure and posed ongoing erosion and flooding risks.
To protect public safety and secure the vital transport corridor, Lac Ste. Anne County amended its capital budget to fast-track an Emergency Culvert Replacement and Road Repair. Key structural upgrades included:
- Culvert Removal: Full removal and disposal of the failing 900 mm corrugated steel pipe (CSP) culvert (42.2-metre invert length).
- Expanded Capacity: Installation of a significantly larger 1,600 mm diameter CSP culvert spanning 64 metres to accommodate higher water volumes and reduce future flood risks.
- Surface Restoration: Comprehensive road reconstruction, seamless transition joint fitting, and repaving completed in partnership between project contractors and County Public Works staff.
Following tender procurement in early 2026, emergency mitigation began this May, leading into major site work that commenced on July 7.
"When structural failures and severe flooding threatened this key route right past our local school area, Council moved quickly to approve emergency funding and protect our community. Seeing the contractor and our Public Works crew work to reopen the road eight days ahead of schedule is a fantastic outcome. We deeply appreciate the hard work of everyone involved."
The County extends its appreciation to local commuters, agricultural operators, and families in the Mayerthorpe area for their cooperation and understanding throughout the construction period.